Thai navy must retender frigate program after appeal upheld over tender flaws

Thailand's Appeals and Complaints Committee has ordered the Royal Thai Navy's frigate tender cancelled, the navy said, after upholding one appeal over procedural flaws. Hanwha Ocean had been preferred bidder.

Thailand's Appeals and Complaints Committee has ordered the Royal Thai Navy's frigate tender cancelled, the navy said, after upholding one appeal over procedural flaws. Hanwha Ocean had been preferred bidder.

The Royal Thai Navy must retender its frigate program after the Appeals and Complaints Committee under the Comptroller General's Department ordered the tender cancelled, navy spokesman Rear Adm. Chanin Sriyaphai announced on Nov. 18.

The deal

  • Buyer Royal Thai Navy
  • Preferred bidder Hanwha Ocean (Ocean-40F)
  • Contract value THB16.73 billion (US$508 million)
  • Decision Tender cancelled after appeal upheld
  • Contract deadline End of September 2027

The committee upheld one appeal, from the Thai Frigate Building Consortium, a joint venture with Navantia. It argued that the terms of reference did not specify monetary thresholds for bidders' past shipbuilding track records. Four other appeals were rejected. Hanwha Ocean had been the only bidder to pass qualification with its Ocean-40F design, and the THB16.73 billion (US$508 million) contract was never awarded.

Chanin said the navy acknowledged the terms were incomplete and did not comply with regulations, and denied any corruption or favoritism. Navy chief Adm. Nares Wongtrakul said the service would respect the legal process.

Naval News reported that a new tender will take another six months to prepare, with new committees required, and that the contract must be signed by the end of September 2027 to use the current budget. The navy does not expect to be liable for damages.

Local media reported that Hanwha Ocean petitioned Thailand's State Audit Office on Nov. 18. It remains eligible to bid again but will have no favored status.

Frequently asked questions

Why was the Royal Thai Navy frigate tender cancelled?

The Appeals and Complaints Committee upheld an appeal that the terms of reference did not properly specify monetary thresholds for bidders' past shipbuilding experience, as Ministry of Finance rules require.

Who was the preferred bidder for the Thai frigate?

Hanwha Ocean, with its Ocean-40F design, was the only bidder to pass qualification. Its contract was never awarded, and it can bid again in the new tender.

When must the new Thai frigate contract be signed?

Naval News reported that the navy must sign by the end of September 2027 to use its allocated budget for the current fiscal period.

Sources: Naval News.

AI-assisted: drafted with AI from the sources above and reviewed by an editor.