The Defence Infrastructure Organisation has handed back a fully replaced runway at RAF Brize Norton after 16 weeks. It is part of a £180 million airfield overhaul due to finish late in 2027.
The RAF Brize Norton runway has been fully replaced in 16 weeks, and aircraft have returned to the station, according to the Defence Infrastructure Organisation (DIO). The 3km runway is part of a £180 million programme to overhaul the airfield.
Key facts
- Site RAF Brize Norton
- Runway length 3km
- Replacement time 16 weeks
- Programme value £180 million
- Contractors VolkerFitzpatrick, AECOM
- Completion Late 2027
The DIO handed the runway back to Air Commodore Phil Reid, Head of Air Infrastructure, on behalf of the RAF. The first aircraft landed on the new surface on Friday 13 November. VolkerFitzpatrick carried out the work, with AECOM providing technical services.
The runway is built from Pavement Quality Concrete and Grooved Marshall Asphalt, chosen to cope better with higher temperatures. The DIO said the concrete is expected to more than double the runway's service life compared with the previous materials.
While the runway was closed, the RAF said its Voyager tankers operated from Glasgow Prestwick, East Midlands and Stansted. The Atlas and C-17 Globemaster fleets moved mainly to MoD Boscombe Down, with occasional use of Bournemouth Airport.
What happens next
The rest of the programme, funded through the Defence Investment Plan, covers refurbishing taxiways, upgrading airfield lighting and improving drainage. Reid said the team effort will continue through to overall project completion late in 2027.
Frequently asked questions
How long did the RAF Brize Norton runway replacement take?
The DIO says the 3km runway was fully replaced in 16 weeks. The first aircraft landed on the new surface on Friday 13 November.
Where did RAF aircraft operate from during the closure?
Voyager tankers used Glasgow Prestwick, East Midlands and Stansted. Atlas and C-17 fleets moved mainly to MoD Boscombe Down, with occasional use of Bournemouth Airport, the RAF said.
When will the Brize Norton airfield programme finish?
The £180 million programme, which also covers taxiways, lighting and drainage, is due to finish late in 2027.
Sources: UK Defence Journal.
AI-assisted: drafted with AI from the sources above and reviewed by an editor.