Naval · United Kingdom

UK minister says Devonport 10 Dock upgrade faces issues with original 2027 delivery date

Defence Readiness Minister Luke Pollard says assurance reviews found problems with the original 2027 delivery date for the Devonport 10 Dock upgrade, though the project has entered construction. The MOD is working to recover the programme.

Defence Readiness Minister Luke Pollard says assurance reviews found problems with the original 2027 delivery date for the Devonport 10 Dock upgrade, though the project has entered construction. The MOD is working to recover the programme.

The upgrade of 10 Dock at Devonport, where Royal Navy submarines are maintained, has entered construction, but reviews have found problems with its original 2027 delivery date, according to a written parliamentary answer from Luke Pollard, Minister for Defence Readiness and Industry.

The numbers

  • Facility 10 Dock, Devonport
  • Original date 2027
  • Current phase Construction, dockside buttresses begun
  • Programme with challenges Submarine Waterfront Infrastructure Future (SWIF)
  • Source Written answer from Luke Pollard

Pollard was responding to Ben Obese-Jecty, the Conservative MP for Huntingdon, who asked whether the upgrade would be completed to its original schedule. He said the government inherited a number of late and delayed programmes.

He said the Ministry of Defence (MOD) and the National Infrastructure and Service Transformation Authority (NISTA) assurance processes had highlighted issues with the 2027 date. Pollard said progress had been made, with 10 Dock recently moving into construction as work began on the dockside buttresses.

He added that challenges remain with delivery of the Submarine Waterfront Infrastructure Future (SWIF) programme. The MOD is working with NISTA and the contractor to recover the programme, and is reviewing opportunities to accelerate the work following the Nuclear Regulatory Review, he said.

Background to the submarine maintenance backlog

UK Defence Journal reported that a shortage of dry docks able to take nuclear submarines has been a major cause of low availability among the Royal Navy's attack submarines, with boats queuing for maintenance.

Frequently asked questions

Is the Devonport 10 Dock upgrade delayed?

Minister Luke Pollard said MOD and NISTA assurance processes highlighted issues with the original 2027 delivery date. He did not give a new date.

What stage is the 10 Dock upgrade at?

Pollard said 10 Dock has moved into the construction phase, with work started on the dockside buttresses.

What is the MOD doing to recover the programme?

The MOD is working with NISTA and the contractor, and is reviewing ways to accelerate work following the Nuclear Regulatory Review.

Sources: UK Defence Journal.